Rogun Hydro Project

in Aral Sea Basin, Tajikistan

335 metres

the tallest dam in the world

60,000

expected number of displaced people

ADB Considers $500 Million Support for Tajikistan’s Rogun Hydropower Plant

The Asian Development Bank (ADB) will continue supporting Tajikistan’s Rogun Hydropower Plant (HPP) project in 2025, the bank’s new country manager, Ko Sakamoto, announced on February 25.

Speaking to reporters, Sakamoto emphasized that Rogun HPP is a top priority for the Tajik government, highlighting its significance for Tajikistan’s energy independence, regional stability and climate change mitigation.

The ADB has been invited to join a consortium of financial institutions financing the project. Tajikistan has requested $500 million in assistance, and the bank is currently reviewing the proposal.

“ADB will continue to support the project and share updates as negotiations progress,” Sakamoto said.

In 2024, ADB provided $220 million in assistance to Tajikistan, funding six projects across agriculture, energy, health, public administration and transport. ADB plans to approve four new projects in 2025, including an initiative on digital agriculture aimed at boosting food security.

The bank is developing a five-year strategy that will align with Tajikistan’s long-term development goals. It will support glacier protection efforts, as Tajikistan leads regional climate initiatives. An international glacier conservation conference is scheduled for May in Dushanbe.

As Tajikistan works toward greater energy security, Rogun remains central to its economic and environmental strategy. ADB’s continued involvement signals strong international backing for the project, which has the potential to transform Tajikistan into a key regional energy exporter. If approved, the $500 million in funding would mark a significant step toward completing one of Central Asia’s most ambitious hydropower projects.

Leave a Reply

Your email address will not be published. Required fields are marked *

Search

Popular Posts

  • Rogun Dam Assessment Fails to Meet Standards, Report Finds
    Rogun Dam Assessment Fails to Meet Standards, Report Finds

    A report by the international environmental coalition Rivers without Boundaries, titled “With Eyes Wide Shut: Ignoring the Transboundary and Cumulative Impacts of the Rogun HPP,” concludes that the project’s environmental and social impact assessment has fundamental shortcomings and does not fully comply with World Bank standards. The review of the giant hydropower plant project in…

  • Rogun HPP Financing: ADFD Supports Tajikistan’s Energy Security
    Rogun HPP Financing: ADFD Supports Tajikistan’s Energy Security

    Abu Dhabi Fund for Development has agreed a new loan with the Government of the Republic of Tajikistan to support the Rogun Hydroelectric Power Station, a major scheme that aims to secure reliable electricity, build large-scale water storage and strengthen regional energy links across Central Asia. The financing, worth AED376 million, is arranged within the…

  • Tajikistan increases Rogun HPP funding using domestic resources
    Tajikistan increases Rogun HPP funding using domestic resources

    On January 22, the lower house of Tajikistan’s parliament passed the bill “On the Use of the National Bank of Tajikistan’s Reserve Fund,” which is aimed at financing the construction of the Rogun HPP. The bill was developed at the initiative of the country’s President, Emomali Rahmon, according to “Sadoi Mardum”, the official newspaper of…